The physical execution rate of the medium- and low-voltage network construction works for the electrification of 280 localities in the Far North, East, and North-West is 51.13%.
Electrification works are almost completed in the East. Commissioning is underway. One thousand five hundred connection applications have been collected from households.
In the Far North, the works will resume shortly after the end of the rainy season.